Work taking place by DART contractors in the DART Silver Line corridor will necessitate the following new lane closures:
- Southbound North Central Expressway frontage road between Plano Parkway and Renner Road, and the US 75 exit ramp just south of Plano Parkway, will be closed overnight beginning Monday, Oct. 20 at the following times, as the Silver Line US 75 bridge archway is constructed:
Monday-Thursday 9 p.m.-4 a.m.
Fridays 10 p.m.-6 a.m.
Saturdays 10 p.m.-8 a.m.
Drivers should expect delays during these times and plan alternate routes. The work is expected to wrap up by Nov. 17.
- The left lane of the eastbound Bush Turnpike frontage road between Red Moon Way and Routh East Drive, and Routh East Drive under the Bush Turnpike bridge may be fully closed to traffic at all times as work takes place related to the new Silver Line hike and bike trail. Routh East Drive traffic will be detoured to Plano Road for a U-turn under the bridge. The work is expected to be completed by late October.