Road workers have staged the box culverts for this weekend’s work that will require the closure of Main Street just east of US 75.
This will be the only full closure of the road required for the reconstruction project and will impact the road between McKinney St. and Interurban St. from Saturday, Feb. 8 to late Sunday, Feb. 9.
The work will be complete in time for morning drive-time traffic on Monday, Feb. 10.
The construction is dependent on weather and may be delayed if the weather becomes inclement. Motorists are advised to seek an alternative east/west route such as Polk St. or Arapaho Rd.