The City Council was given an overview of the City’s 5-year Capital Improvement Plan Monday, including the implementation plan for Year 1 of the 2021 Bond Program as well as a look at other capital projects underway over the next five years. The near-$400 million in projects (the highest five-year investment in projects in the City’s history) includes:

Project Category Total Amount 
2015 Bond Program – Remaining Projects $27,825,000 
Utility Improvement Projects $83,512,000 
Special Maintenance Initiatives $28,000,000 
2021 Bond Program Projects $190,000,000 
(+$34,500,000 in other sources) 
Street & Alley Annual Maintenance Programs $31,845,000 
Total$395,682,000 

Because of the extensive number of projects planned, the City has hired local engineering firm AECOM to act as general engineering consultant and augment City staff project management duties. An AECOM team of 2-6 people will be housed at City Hall over the next 5-7 years.

Website: Watch Monday’s Presentation