As Phase 3 of the Campbell Auxiliary Lane Project, the left lane of westbound Campbell Road between US 75 and Prairie Creek Drive may be closed to traffic from 9 a.m.-3:30 p.m. for street light removal and reinstallation. The work is expected to be complete by mid-May.

In addition, the right lanes of both eastbound and westbound Campbell Road between Coit Road and Lennox Square Place, and also the outside left turn lane of southbound Coit Road onto eastbound Campbell Road may be closed to traffic from 9 a.m.-3:30 p.m. for cable installation. The work is expected to be complete by early August.