The final phase of the FY25 Annual Street Maintenance work involving concrete panel replacement is set to begin Monday, May 4, weather permitting. Part 1 takes place along a segment of Belt Line Road between Bowser Road and Plano Road, westbound lanes and then eastbound. During the work, one lane will be closed at all times with another lane closure possible during non-peak hours from 9 a.m.-3:30 p.m. The work is expected to be complete by the middle of June.  

Once completed, crews will move west on Belt Line between Walton Street and Bowser Road to complete the second and final part of the work.